Tyndall AFB, Panama City, FL - Sanitary Sewer Survey and Rehabilitation

 

TOTAL LF: 67,000’ of 8" - 12"

 

PROJECT SCOPE:

Clean and televise sanitary sewer to determine extent of damage and recommend the most effective method of rehabilitation. The pipe was a variety of RCP, VCP and PVC, and contained heavy debris. The MIDAS Trenchless crew had to work within a controlled and high security environment that resulted in short working hours and several delays due to military drills.

 

RESULT:

Despite the strict working hours and delays beyond our control, we completed the project ahead of schedule and delivered very detailed survey reports that assisted the base in determining the applicable repair method.

 

 

North Little Rock, AR - 2013 CIPP Rehabilitation Project

 

Total LF: 17,000’ 6" - 24"

 

PROJECT  SCOPE:

Clean and televise sanitary sewer to prepare for CIPP and pipe bursting. The pipe, made of clay and RCP, exhibited extensive root intrusion, off-set joints, debris and heavy flow conditions. The MIDAS Trenchless Solutions crew dealt with limited access due to easement restrictions, an inordinate amount of root removal and numerous reverse setups.

 

RESULT:

The project was completed on time and to the satisfaction of the contractor.

 

 

Pasadena, TX - Vista Street Sanitary Sewer Rehabilitation

 

TOTAL LF: 12,000 LF 24" - 30”

 

PROJECT  SCOPE:

Clean, televise, and prepare report of the condition of the sanitary sewer for CIPP. The MIDAS Trenchless Solutions crew successfully removed heavy debris and obstructions from the RCP line as part of the prep work. The crew also cleaned a siphon not originally listed on the plan.

 

RESULT:

Project completed on time and to the satisfaction of the contractor.

 

 

Deer Park, TX - Sanitary Sewer Rehabilitation of Priority Area #3

 

TOTAL LF: 44,000’ 6" - 10"

 

PROJECT  SCOPE:

Clean, televise, and prepared a combination of RCP and HDPE sanitary sewer for pipe bursting. The MIDAS Trenchless Solutions crew overcame exceptionally long runs, protruding services, and stabilized material in pipe.

 

RESULT:

Completed the project on time and to the satisfaction of the contractor.

 

 

PHOTO GALLERY

MID-ATLANTIC REGION:  9200 Edgeworth Drive  |  Capitol Heights, MD 20743  |  P: 301.474.4888  |  F: 301.441.8170  |  HR@midascompanies.com

SOUTH CENTRAL REGION:  9155 Wallisville Road  |  Houston, TX 77029   |  P: 713.750.9081  |  F: 832.201.7828  |  HR@midascompanies.com

CORPORATE OFFICE:  9200 Edgeworth Drive  |  Capitol Heights, MD 20743  |  P: 301.474.4888  |  F: 301.850.2762  |  HR@midascompanies.com